Uni Pole Erection Process

Video

GENERAL TECHNICAL SPECIFICAION BEING USED TOWARDS UNIPOL ERECTION

Main pole   950 Dia 8mm thickness
Horizontal pipe 410 dia 6mm thickness 8 nos
Base plate 1500 x 1500 32 mm thickness 1 nos
Top Base  Plate 1250 x 1250 x 16mm 10 nos
Connecting base plate 500 x 350 12mm thickness 50 nos
Connecting plate  500 x 200 12mm thickness 50 nos
I Beam  100 x 50  quantity 25 nos
65mm, 65mm, 6 mm L angle 50 nos
55mm , 55mm, 6mm L angle 50 nos
Monkey Ladder display frame 1 x 1 ¼ square tube 210 nos
Foundation patel  fishing Rod 12mm & 10mm 250 kg
32mm dia thickness foundation bolt (6 mts) 8 nos
Sand 3 unit blue metals units coromondal cement 70 bags.
Foundation  10 ft depth 5 x 5 . & civil work
 
Work completion duration   maximum 12 days  if there is no rain